Umatilla Electric Cooperative’s commitment to powering our region with reliable, forward-thinking infrastructure continues with steady progress on the Umatilla-Morrow County Connect (UMCC) Project. The proposed 14-mile, 230-kilovolt (kV) high-voltage transmission line is a major step in strengthening the electrical backbone of our region - connecting Umatilla and Morrow counties while paving the way for increased energy resiliency, capacity, and support for Oregon’s growing energy needs.
At the end of May, the UMCC Project has reached an important milestone in the State of Oregon’s Energy Facility Siting Council (EFSC) process: the submission of UEC’s Application for a Site Certificate (step three of the six-step EFSC process).
This marks the beginning of an intensive review by the Oregon Department of Energy (ODOE) and other state agencies to ensure the project meets all applicable standards and regulations. Within approximately 90 days, a public meeting will be scheduled to allow interested community members to learn more and provide input.
What Is the UMCC Project?
The UMCC Project proposes a 14-mile, 230 kV transmission line connecting UEC’s Highway 730 Switchyard to the Ordnance Switchyard. This new infrastructure will enhance the cooperative’s high-voltage transmission network, creating a crucial link between Umatilla and Morrow counties. Once complete, the line will:
- Improve power reliability and resiliency for communities and industries in the region.
- Expand UEC’s 230 kV transmission system to meet current and future demand.
- Support regional economic development and growth.
- Provide a transmission pathway for renewable energy projects across Eastern Oregon.
Why the EFSC Process?
Projects like the UMCC transmission line must undergo a rigorous state-level review when they meet all of the following criteria:
- The total project length exceeds 10 miles
- The project operates at 230 kV or higher, and
- The project spans multiple jurisdictions
EFSC, an independent seven-member council appointed by the Governor, evaluates these large-scale energy infrastructure projects to ensure they meet Oregon’s strict environmental, land-use, and public interest standards.
The Site Certificate process includes multiple phases with opportunities for agency coordination and public involvement. UEC has already completed the Notice of Intent and received a Project Order outlining all applicable rules and permit requirements. The current phase, Application for a Site Certificate, involves review by numerous state and tribal agencies, including Oregon Department of Fish and Wildlife, Oregon Department of Transportation, Department of Environmental Quality, and local governments.
Once the application is deemed complete, ODOE will release a Draft Proposed Order and host a public hearing, where stakeholders and members of the public are encouraged to provide comments.
Looking Ahead
UEC anticipates ODOE hosting a public meeting on the UMCC Project within the next 90 days and encourages UEC members to participate and learn more about how this project benefits our shared future. As our region continues to grow, reliable and modern infrastructure is essential.
The UMCC Project not only strengthens the backbone of our electrical system but also opens doors to increased renewable energy integration, economic opportunity, and community resilience.
For more details on the project timeline, siting process, and upcoming public involvement opportunities, please visit: www.umccproject.com.