Location: Boardman, OR

 

To support growth in Boardman, UEC is added a new 230 kV transmission line from the cooperative’s existing Highway 730 Switchyard to Bonneville Power Administration’s Longhorn Substation. The added capacity allows UEC to better serve members in the region with resilient and reliable energy.

Anticipated Construction Schedule

Start Date: June 2024

Completion Date: January 2025

Why Add Capacity?

UEC needs to invest in new infrastructure to meet the increased need of the rapidly growing region. The added transmission line will support anticipated industrial and commercial growth, fostering the economic development within Morrow county.

UEC’s Commitment to Our Membership

Transmission lines are critical links in the electric distribution system. As our communities continue to grow, UEC is committed to investing in the infrastructure to serve our members.

Benefits and Value Carefully Considered

UEC members and community may experience construction activity along the intersection of Highway 730 and Interstate I-84, with minimal impact to traffic. Members and the community can expect to see a mix of new structures while also utilizing some existing structures. Traffic control will be present intermittently as crews are drilling holes, setting poles, and installing conductor.

UEC will continue to address the area’s growing energy needs to ensure we can continue to provide reliable power for years to come.